2017/1/11
Nano-porous insulation board is a new type of thermal insulation material, than the traditional ceramic fiber board insulation performance 4 times better, does not contain asbestos and ceramic fiber, on the human body and the environment without any side effects, in line with the latest European environmental requirements. So you know the nano-porous insulation board construction process? Want to know, then follow the Chinese insulation network Xiaobian together to see it down.
1, positioning: According to the shape of porous insulation board, select the location of porous insulation board paste, try not to cut porous insulation board, do not penetrate the porous insulation board to maintain the integrity of porous insulation board, To save material;
2, Alignment: In order to maintain the upper part of the lining openings openings neatly, the use of top-down construction, the upper part of the construction requirements of microporous insulation board alignment; up and down microporous insulation board to close, in principle The smaller the gap the better;
3, cutting: the special-shaped parts, the need to cut porous insulation board, the requirements of steel tape measure the exact size, and then the micro-porous insulation board flat on the ground, with steel ruler in the porous insulation board to take Size, the requirements of accurate to millimeters, does not allow roughly the same, just gestures; cut microporous insulation board, with a steel ruler to suppress the tangent, first with a paper knife against the steel ruler, gently micro-hole insulation Board surface of the aluminum foil scribe, and then forced along the tangent cut off the porous insulation board powder, and finally cut off the lower part of the aluminum foil insulation blanket packaging;
4, sealed: cut the porous insulation board, to immediately seal the incision with aluminum foil tape to prevent leakage of powder, not part of the microporous insulation plate gently flat on the reserve;
Note: two incisions to be immediately sealed with aluminum foil tape to prevent leakage of powder and damage;
5, the openings: the need to pass through the microporous insulation board insulation, with a dedicated knife in the middle of the alignment anchor position, careful not to cut too much, do not deviate from the middle anchor position, carefully Cut incision, the incision should not be too large, do not deviate from the anchoring of the median position;
6, Drilling: If you need to drill in the field you need to use the upper and lower two plastic plates, the board opened a good hole, with a plastic plate to pinch the porous insulation board, and then drill with an electric drill accurate;
7, seams: the gap for large areas, you can use cutting off the trim of filling, external aluminum foil tape paste live.